Skip to main content
U.S. flag

An official website of the United States government

Here’s how you know

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock (LockA locked padlock) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

    • Environmental Topics
    • Air
    • Bed Bugs
    • Cancer
    • Chemicals, Toxics, and Pesticide
    • Emergency Response
    • Environmental Information by Location
    • Health
    • Land, Waste, and Cleanup
    • Lead
    • Mold
    • Radon
    • Research
    • Science Topics
    • Water Topics
    • A-Z Topic Index
    • Laws & Regulations
    • By Business Sector
    • By Topic
    • Compliance
    • Enforcement
    • Laws and Executive Orders
    • Regulations
    • Report a Violation
    • Environmental Violations
    • Fraud, Waste or Abuse
    • About EPA
    • Our Mission and What We Do
    • Headquarters Offices
    • Regional Offices
    • Labs and Research Centers
    • Planning, Budget, and Results
    • Organization Chart
    • EPA History

Breadcrumb

  1. Home
  2. East Palestine, Ohio Train Derailment

Newsletter: East Palestine Train Derailment Response, 2-14-2024

Newsletter serving Serving East Palestine, Negley, Darlington, and surrounding communities

On this page:
  • Progress Made
  • The Look Ahead
  • Project Spotlight
  • Community Corner
  • In the News
  • Reponse by the Numbers
  • About this Publication
  •  

Progress Made

Aerial view of the main area of the train derailment showing land cleaned and backfilled with stone

Backfilling Excavated Areas

Backfilling operations in Car Scrapping Area 4 are now complete. Over the last few weeks, as many as 100 trucks a day delivered clean stone and gravel into this excavated area where it was then graded and leveled. The next step is to restore Car Scrapping Area 4, which may include adding another foot or so of finer material like sand or topsoil. Also, there are some additional site areas that still need backfill, but these smaller-scale operations will require much less volume of fill than Car Scrapping Area 4.

An on-the-ground view of grading in the main derailment area

Easing Taggart Street Traffic Restrictions

Truck traffic on E. Taggart Street will decrease with the completion of major backfilling operations in Car Scrapping Area 4. As this heavy equipment traffic eases, E. Taggart Street traffic controls will be reduced, including fewer cones and signage. The speed limit will remain at 15 mph to ensure both community and worker safety while site restoration and other work continue.

The Look Ahead

Timeline of site activities in East Palestine
This schedule is an estimate and is subject to change based on several factors, including without limitation, obtaining required regulatory approvals, access, weather, equipment malfunctions, receipt of laboratory results, etc. Click to enlarge for printing.
Anticipated Completion in Actions
June Site restoration (and water flow to North & South ditches)
July Creek assessment and cleanup
September Demobilize wastewater treatment plant, tank farms, staging areas, offices
September Restore roadways/traffic
October Site characterization/confirmatory soil sampling (Appendix E)
October Surface water, groundwater, drinking water monitoring (prior to transition to long-term monitoring)
Ongoing until site work is complete Communications (outreach, press, community relations)

Project Spotlight: Wastewater & Surface Water Update

Trucks are loaded with non-hazardous water for off-site disposal
Trucks are loaded with non-hazardous water for off-site disposal

Wastewater Management and Disposal

Throughout the response, rainwater and snow melt that have touched potentially contaminated soil areas have been collected and put into storage tanks. Initially, this water was then shipped to off-site disposal facilities as hazardous waste. Following construction of the on-site wastewater treatment plant (WWTP) most collected water has been sent through the treatment system before being shipped off-site as nonhazardous waste.

Now that all contaminated soils have been removed, and after many months of testing the collected water before on-site treatment, it has been determined that it can be disposed of as non-hazardous even without treatment if it is first tested to show it doesn’t contain vinyl chloride and other hazardous materials’. This represents great progress, is a significant step towards final site restoration and reflects how successful the removal of contamination has been.

Planning for the final phases of water management, and endpoints for when it will no longer be necessary to collect and manage it as waste, are underway and will be described in upcoming newsletters.

Creek Assessment and Cleanup Update

In the coming weeks, keep an eye out for summary reports from recent creek assessment work. Also, an interactive map detailing the sheen survey has been added to the website. EPA has previously posted all of its sediment sampling results to its website, which includes data from February, summer, and late fall of 2023. Planning is underway for additional cleanup actions necessary to address sheen and sediment contamination that will begin in early spring. Details of these plans will be explained as they are finalized.

Community Corner

Sound the Alarm Campaign 

In the village of East Palestine, the American Red Cross is partnering with the fire department to install free smoke alarms for residents who don’t have adequate smoke alarms (one per each level of the home). Please check the EPFD Facebook page for the registration form and additional details.

In the News: Dioxins and Data Availability

Some recent news reports made an inaccurate claim that EPA failed to openly share data, particularly the waste-characterization data that was collected in February 2023 related to dioxin and furan compounds. Early in the response, EPA started sharing dioxin data from characterized site waste with the public. This data sharing occurred through many meetings with community members at EPA’s welcome center and at broader community meetings and events. EPA made this data publicly available on its webpage and has openly discussed it throughout the response. The dioxin and furan levels detected while characterizing derailment site wastes for disposal were not unusual for this type of waste and were managed safely throughout the cleanup. EPA remains committed to scientific integrity and transparency of its data and data collection methodology.

Response by the Numbers

Waste

Over 176,000 tons more than 350 million pounds of contaminated soil*

201 drums of site-related material contained*

49 million gallons of contaminated liquid managed*

*shipped off-site for certified disposal


Samples

  • 1,025 groundwater
  • 28,000 air
  • 3,872 surface water
  • 233 sediment
  • 1,309 private well
  • 6,323 soil
  • 288 public drinking water

Fact Sheet Coming Soon

More details on wastewater and surface water, plus information on the status of additional cleanup activities for Sulphur and Leslie Runs, will be mailed in a separate fact sheet.

snapshot of newsletter in development
Example of a factsheet shared in May

About This Publication

This newsletter is developed through a joint effort of state and federal agencies and community organizations. If you would like more information about topics discussed, please visit: East Palestine, Ohio Train Derailment Emergency Response website or call EPA’s Information Line at 330-775-6517.

PDF version: Newsletter: East Palestine Train Derailment Response, February 14, 2023 (pdf) (2.72 MB)

East Palestine, Ohio Train Derailment

  • East Palestine, Ohio Train Derailment Home
  • Operational Updates
  • Resources for Affected Residents
    • Public Health Resources
    • Home and Office Cleaning
    • Settlement Update
  • Air Monitoring and Sampling Data
    • About Air Monitoring
    • Air Sampling Data
    • Air Monitoring Documents
  • Soil and Sediment Data
    • Soil and Sediment Sampling Data
    • Phase One Residential, Commercial, and Agricultural Soil Sampling Results
    • Soil and Sediment Sampling Results Quick Reference Guide
    • Event Reconstruction Plume Map
    • City Park Soil Sampling Results
    • Qualitative Sheen Assessment Results
    • Response to Inaccurate Dioxin Reporting
    • Workplan to Cleanup Sediment in Sulphur and Leslie Runs
  • Water Sampling Data
    • Water Management Update
  • Data Validation Reports: Air, Soil, Water
  • Photos
  • Videos
  • Newsletters
  • Legal and other documents
    • About Executive Order 14108
    • Clean Water Act Administrative Order and Directives
    • Full Characterization Workplan
  • Frequently Asked Questions
    • About Soil Sampling
    • Taggart Street Reopening
  • Background
  • News Releases
Contact Us About the East Palestine, Ohio Train Derailment
Contact Us to ask a question, provide feedback, or report a problem.
Last updated on March 14, 2025
  • Assistance
  • Spanish
  • Arabic
  • Chinese (simplified)
  • Chinese (traditional)
  • French
  • Haitian Creole
  • Korean
  • Portuguese
  • Russian
  • Tagalog
  • Vietnamese
United States Environmental Protection Agency

Discover.

  • Accessibility Statement
  • Budget & Performance
  • Contracting
  • EPA www Web Snapshot
  • Grants
  • No FEAR Act Data
  • Plain Writing
  • Privacy
  • Privacy and Security Notice

Connect.

  • Data
  • Inspector General
  • Jobs
  • Newsroom
  • Regulations.gov
  • Subscribe
  • USA.gov
  • White House

Ask.

  • Contact EPA
  • EPA Disclaimers
  • Hotlines
  • FOIA Requests
  • Frequent Questions
  • Site Feedback

Follow.