Title V Operating Permit Public Petition Deadlines
The table below lists proposed Title V permits submitted to EPA and undergoing EPA's 45 day review, including the start and expiration dates for EPA's 45 day review period. It also shows the start and expiration dates for the public's 60 day petition period following EPA's review period.
Hint: Click on a column heading to sort the table by that column. Table data last updated on July 11, 2025.
State | Facility Name | FRS No. | Permit No. | EPA 45-day Review Period Start Date | EPA 45-day Review Period End Date | 60-day Public Petition Period Start Date | 60-day Public Petition Period End Date | Permit Action |
---|---|---|---|---|---|---|---|---|
DE | DuPont Experimental Station | 110000771807 | AQM-003-00011 (Renewal 3) | 04/11/2025 | 05/26/2025 | 05/27/2025 | 07/25/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
MD | Sunoco - Baltimore Terminal | 110016741659 | 24-510-0703 | 06/18/2025 | 08/01/2025 | 08/02/2025 | 09/30/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
MD | National Security Agency | 110000796112 | 24-003-0317 | 06/10/2025 | 07/24/2025 | 07/25/2025 | 09/22/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
MD | JHMI Utlities, LLC | 110001276128 | 24-510-0001 | 05/30/2025 | 07/14/2025 | 07/15/2025 | 09/12/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
MD | Social Security Administration | 110000835151 | 24-005-00282 | 05/06/2025 | 06/19/2025 | 06/20/2025 | 08/18/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
MD | Evonik Corporation | 110019864547 | 24-025-0005 | 04/18/2025 | 06/02/2025 | 06/03/2025 | 08/01/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
PA | Exelon Schuylkill | 110000337029 | OP23-000050 | 07/12/2025 | 08/25/2025 | 08/26/2025 | 10/24/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
PA | Exelon Delaware | 110000336716 | OP23-000043 | 07/12/2025 | 08/25/2025 | 08/26/2025 | 10/24/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
PA | Wood Mode Inc | 110000334488 | 55-00005C | 07/08/2025 | 08/21/2025 | 08/22/2025 | 10/20/2025 | MERGED PERMIT |
PA | Curry Rail Service Inc. | 110067426921 | 07-05045 | 06/30/2025 | 08/13/2025 | 08/14/2025 | 10/13/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
PA | YORK GROUP INC/BLACK BRIDGE RD | 110000333434 | 67-05014D | 06/25/2025 | 08/08/2025 | 08/09/2025 | 10/07/2025 | MERGED PERMIT |
PA | Cleveland Cliffs Monessen | 110000329118 | 65-00853B | 06/25/2025 | 08/08/2025 | 08/09/2025 | 10/07/2025 | MERGED PERMIT |
PA | Moxie Freedom LLC | 110064098541 | 40-00129 | 06/24/2025 | 08/07/2025 | 08/08/2025 | 10/06/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
PA | Braskem Amer Inc Marcus Hook | 110000584706 | 23-00012 | 06/20/2025 | 08/04/2025 | 08/05/2025 | 10/03/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
PA | USA Waste (Chambers Development Company/ Monnroeville) | 110007336622 | 0051-OP23a | 06/11/2025 | 07/25/2025 | 07/26/2025 | 09/23/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
PA | ETMT/Marcus Hook Industrial Complex | 110032885723 | 23-00119 | 06/06/2025 | 07/21/2025 | 07/22/2025 | 09/19/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
PA | PA STATE UNIV/ Univ Park Campus | 110064200350 | 14-00003 | 05/28/2025 | 07/11/2025 | 07/12/2025 | 09/09/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
PA | Dominion Trans Inc Tioga | 110012199245 | 59-00002 | 05/27/2025 | 07/10/2025 | 07/11/2025 | 09/08/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
PA | Westmoreland Sanitary Landfill | ------ | 65-00767 | 05/23/2025 | 07/07/2025 | 07/08/2025 | 09/05/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
PA | Pixelle Specialty Solutions LLC | 110017404664 | 67-05004 | 05/22/2025 | 07/07/2025 | 07/08/2025 | 09/05/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
PA | Constellation Energy Chester | 110008470500 | 23-00018 | 05/15/2025 | 06/30/2025 | 07/01/2025 | 08/29/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
PA | East Penn Manufacturing- Battery Assembly | 110043973322 | 06-05069AF | 05/16/2025 | 06/30/2025 | 07/01/2025 | 08/29/2025 | MERGED PERMIT |
PA | Salem Tube Inc./Greenville Reynolds Industrial Park | 110000331061 | 43-00142 | 05/14/2025 | 06/27/2025 | 06/28/2025 | 08/26/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
PA | Mersen USA St Marys PA Corp | 110063077272 | 24-00083AD | 05/12/2025 | 06/25/2025 | 06/26/2025 | 08/25/2025 | MERGED PERMIT |
PA | Buck Co, Inc. | ------ | 36-05053 | 05/12/2025 | 06/25/2025 | 06/26/2025 | 08/25/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
PA | Altoona Terminals DE LLC | 110043693777 | 07-05004B | 05/02/2025 | 06/16/2025 | 06/17/2025 | 08/15/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
PA | NRG Power Midwest LP New Castle Power Plt | 110010259451 | 37-00023 | 04/24/2025 | 06/09/2025 | 06/10/2025 | 08/08/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
PA | Calpine, York Energy Center | 110043196528 | 67-05083 | 04/24/2025 | 06/09/2025 | 06/10/2025 | 08/08/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
PA | ALCOSAN | 110001085076 | 0035-OP22a | 04/17/2025 | 06/02/2025 | 06/03/2025 | 08/01/2025 | MINOR MODIFICATION |
PA | Sun Chemical | 110000336761 | OP17-000077 | 04/05/2025 | 05/19/2025 | 05/20/2025 | 07/18/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
VA | Swift Creek Renewables, LLC (PRO52975) | ------ | PRO52975 | 07/14/2025 | 08/27/2025 | 08/28/2025 | 10/27/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
VA | Cascades Containerboard Packaging- Bear Island 819 Virginia LLC | 110000341559 | 50840 | 07/08/2025 | 08/21/2025 | 08/22/2025 | 10/20/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
VA | Strongwell- Highlands | 110000492592 | SWRO 11207 | 06/26/2025 | 08/11/2025 | 08/12/2025 | 10/10/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
VA | Virginia Electric and Power Company-Hopewell Power Station | 110000342629 | 51019 | 06/11/2025 | 07/25/2025 | 07/26/2025 | 09/23/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
VA | Carmeuse-Winchester Lime Plant | 110040906393 | 80504 | 06/11/2025 | 07/25/2025 | 07/26/2025 | 09/23/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
VA | Dominion- Possum Point Power Station | ------ | 70225 | 06/09/2025 | 07/23/2025 | 07/24/2025 | 09/22/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
VA | Appalachian Power Company Clinch River Plant | 110000585581 | 10236 | 06/04/2025 | 07/18/2025 | 07/19/2025 | 09/16/2025 | MINOR MODIFICATION |
VA | Columbia Gas Strasburg Compressor Station | 110005290407 | VRO-81286 | 06/02/2025 | 07/16/2025 | 07/17/2025 | 09/15/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
VA | TransMontaigne Operating Company, L.P. - Fairfax Terminal | ------ | NRO 70306 | 06/03/2025 | 07/17/2025 | 07/18/2025 | 09/15/2025 | SIGNIFICANT PERMIT REVISION |
VA | Transcontinental Gas Pipe Line Company, LLC- Compressor Station 185 | 110007320130 | 71958 | 05/29/2025 | 07/14/2025 | 07/15/2025 | 09/12/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
VA | Covanta Alexandria/Arlington | 110001888743 | NRO71895 | 05/21/2025 | 07/04/2025 | 07/05/2025 | 09/02/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
VA | Hampton/NASA Steam Plan | 110001888994 | 61019 | 05/21/2025 | 07/04/2025 | 07/05/2025 | 09/02/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
VA | BAE Systems Norfolk Ship Repair | 110000342175 | TRO60246 | 05/20/2025 | 07/03/2025 | 07/04/2025 | 09/01/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
VA | Eastman Performance Films, LLC � Axton Plant | 110000585484 | BRRO 30877 | 05/15/2025 | 06/30/2025 | 07/01/2025 | 08/29/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
VA | Terreva Suffolk RNG LLC #61137 | ------ | TRO-61137 | 05/14/2025 | 06/27/2025 | 06/28/2025 | 08/26/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
VA | Dominion Gravel Neck / Surry Power Stations | 110001888459 | 50336 | 04/24/2025 | 06/09/2025 | 06/10/2025 | 08/08/2025 | MINOR MODIFICATION |
VA | Kyanite Mining Corporation | 110020669249 | 30677 | 04/25/2025 | 06/09/2025 | 06/10/2025 | 08/08/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
VA | Quality Investment Properties Richmond PRO-51232 | ------ | PRO-51232 | 04/09/2025 | 05/23/2025 | 05/24/2025 | 07/22/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
VA | Transco Compressor Stations 165 and 166 | 110001893620 | BRRO - 30864 | 04/02/2025 | 05/16/2025 | 05/17/2025 | 07/15/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
WV | Blue Racer Midstream LLC Natrium Extraction and Fractionation Processing Plant | ------ | R30-05100142-2025 | 07/03/2025 | 08/18/2025 | 08/19/2025 | 10/17/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
WV | Chemours Company FC, LLC; Washington Works Facility | 110000586081 | R30-10700182-2021 (Part 2 of 14) | 06/30/2025 | 08/13/2025 | 08/14/2025 | 10/13/2025 | MINOR MODIFICATION |
WV | Covestro LLC - New Martinsville Facility | 110000608030 | R30-05100009-2024 | 06/27/2025 | 08/11/2025 | 08/12/2025 | 10/10/2025 | MINOR MODIFICATION |
WV | Roxul USA, Inc. | 110070936646 | R30-03700108-2024 | 06/06/2025 | 07/21/2025 | 07/22/2025 | 09/19/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
WV | Columbia Gas Transmission, LLC - Lost River Compressor Station | 110006857240 | R30-03100002-2023 | 06/03/2025 | 07/17/2025 | 07/18/2025 | 09/15/2025 | MINOR MODIFICATION |
WV | MPLX Terminals LLC; Kenova-TriState Terminal | ------ | R30-09900022-2020 | 06/03/2025 | 07/17/2025 | 07/18/2025 | 09/15/2025 | MINOR MODIFICATION |
WV | Appalachian Power Company Mountaineer Plant/New Haven, WV | 110000585910 | R30-05300009-2025 | 05/30/2025 | 07/14/2025 | 07/15/2025 | 09/12/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
WV | WIlliams Ohio Valley Midstream LLC Fort Beeler Plant | 110043703267 | R30-05100127-2021 | 05/31/2025 | 07/14/2025 | 07/15/2025 | 09/12/2025 | MINOR MODIFICATION |
WV | Columbia Gas Transmission, LLC; White Oak Station | ------ | R30-01300017-2025 | 05/29/2025 | 07/14/2025 | 07/15/2025 | 09/12/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
WV | Graftech International Holdings Inc.�s Anmoore facility | 110040880320 | R30-03300001-2022 | 05/07/2025 | 06/20/2025 | 06/21/2025 | 08/19/2025 | MINOR MODIFICATION |
WV | Armstrong World Industries, Inc. Armstrong Millwood Plant | 110000772370 | R30-03500049-2025 | 04/25/2025 | 06/09/2025 | 06/10/2025 | 08/08/2025 | MINOR MODIFICATION |
WV | Toyota Motor Manufacturing West Virginia, Inc.�s Buffalo Plant | 110001933169 | R30-07900072-2024 | 04/25/2025 | 06/09/2025 | 06/10/2025 | 08/08/2025 | MINOR MODIFICATION |
WV | Cytec Industries Inc. | 110000344850 | R30-07300003-2021 (Part 2 of 3) | 04/10/2025 | 05/26/2025 | 05/27/2025 | 07/25/2025 | MINOR MODIFICATION |
WV | Columbia Gas Transmission, LLC; Elk River Compressor Station | ------ | R30-03900670-2025 | 04/08/2025 | 05/22/2025 | 05/23/2025 | 07/21/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
WV | Antero Midstream LLC South Canton Compressor Station | ------ | R30-01700163-2025 | 04/05/2025 | 05/19/2025 | 05/20/2025 | 07/18/2025 | INITIAL PERMIT ISSUANCE OR RENEWAL |
WV | Saint Gobain Ceramics and Plastics | 110010443537 | R30-09700001-2020 | 04/02/2025 | 05/16/2025 | 05/17/2025 | 07/15/2025 | SIGNIFICANT PERMIT REVISION |