Search Frequent Questions
Filter By:
-
Risk Management Program (RMP)
Total results: 284
- Applicability/General Duty Clause Total results: 69
- Emergency Response Total results: 6
- Five-Year Accident History Total results: 16
- Offsite Consequence Analysis (OCA) Total results: 57
- Other Risk Management Programs Total results: 34
- Plan Preparation and Submission Total results: 49
- Prevention Program Total results: 30
- Program Levels Total results: 16
- RMP*Comp Total results: 7
- Agriculture Total results: 9
- Air Emissions Inventories Total results: 33
- Asbestos Total results: 141
- Butte Area/Silver Bow Creek Total results: 11
- Compliance Total results: 18
- Coronavirus (COVID-19) Total results: 23
- East Palestine, Ohio Train Derailment Total results: 149
- Emergency Planning and Community Right-to-Know Total results: 267
- Enforcement Total results: 21
- Fuel Program Total results: 648
- Great Lakes Funding Total results: 53
- Indoor Air Quality Total results: 2
- MOVES Total results: 57
- Norwood Landfill Site Total results: 30
- Oil Regulations Total results: 96
- Permitting Under the Clean Air Act Total results: 13
- Public Engagement Total results: 1
- Radiation Total results: 1
- Red Hill Bulk Fuel Storage Facility in Hawai'i Total results: 39
- Smurfit-Stone Mill Total results: 12
- Southeast Minnesota Groundwater Total results: 11
Displaying 61 - 75 of 284 results
-
Active mitigation systems (e.g., scrubbers) and alternative release scenarios
I run a wastewater treatment plant that is subject to the risk management program regulations in 40 CFR Part 68 for a covered process containing chlorine. A chlorine scrubber system at the plant is designed to prevent any possible releases from reaching a toxic endpoint offsite. How does this active…
- Last published:
-
What is the definition of injury?
Under the hazard assessment requirements of 40 CFR Part 68, Subpart B, an owner or operator must document a five-year accident history including all accidental releases from covered processes that resulted in deaths, injuries, or significant property damage on site, or known offsite deaths, injuries, evacuations, sheltering in place, property…
- Last published:
-
Process that meets Program 1 requirements and Program 3 applicability
Program 3 applies to processes in certain NAICS codes as well as any process subject to the OSHA Process Safety Management (PSM) standard, unless the process is eligible for Program 1. If a process meets the requirements of Program 1, but is also in NAICS code 32211 (one of those…
- Last published:
-
When part of a site is sold, what facility ID number is used?
If a site is divided up as part of a sale and part of the site is kept by the original owner and the remainder is sold or leased, what facility ID is used? The section of the site that is retained by the original owner will keep the original…
- Last published:
-
When were RMPs initially required to be submitted?
When must the risk management plans (RMPs) required under 40 CFR Part 68, Subpart G, initially be submitted? For chemicals currently listed as regulated substances at 40 CFR §68.130, compliance with the risk management program requirements (including submission of RMPs) is required by June 21, 1999, or the date on…
- Last published:
-
Program level 3 applicability and whether states have delegated OSHA programs
I am a publicly owned facility in a state with a delegated OSHA program. Why are my processes considered to be in Program 3 when the same processes in a state where federal OSHA runs the program are in Program 2? Federal OSHA cannot impose its rules on state or…
- Last published:
-
Program level 1 eligibility and accident history
A process with more than a threshold quantity of a regulated substance had an accident with off-site consequences three years ago. After the accident, we altered the process to reduce the quantity stored on site, although the quantity still exceeds the threshold quantity. Now the worst case release scenario indicates…
- Last published:
-
Can a process qualify for Program 1 if it has had an accident?
A process with more than a threshold quantity of a regulated substance had an accident with off-site consequences three years ago. After the accident, we altered the process to reduce the quantity stored onsite. Now the worst-case release scenario indicates that there are no public receptors within the distance to…
- Last published:
-
Who should sign the certification statement?
The owner or operator of a stationary source must submit in the RMP a statement certifying that the RMP is accurate and complete (40 CFR §68.185). Who should sign this certification statement? EPA has not promulgated regulations under 40 CFR Part 68 specifying who must sign the certification statement nor…
- Last published:
-
Hot Work Permit Procedures and Date
Stationary sources subject to the Program 3 Prevention Program requirements in 40 CFR Part 68, Subpart D, must include in their Risk Management Plan (RMP) the date of the most recent review or revision of hot work permit procedures in Section 7.13. What are hot work permit procedures and what…
- Last published:
-
Do the quantities of interconnected vessels need to be aggregated for the worst-case release scenario analysis?
Pursuant to the risk management program regulations, facilities must perform an offsite consequence analysis for the worst-case release scenario. Do the quantities of two separate vessels that are interconnected with a closed valve need to be aggregated for the worst-case release scenario analysis? No. Worst-case release is defined as the…
- Last published:
-
Updating RMP if substance no longer held in excess of threshold quantity
If a facility had a covered process that was previously subject to the Program 2 or 3 requirements, but no longer holds the regulated substance in excess of the threshold quantity due to a decrease in production or storage, must the facility update its risk management plan (RMP)? If a…
- Last published:
-
Assigning program level 1 if a public receptors is just beyond distance to endpoint
Our distance to the endpoint for the worst-case release is 0.3 miles. The nearest public receptor is 0.32 miles away. What tools are available to document that the public receptor is beyond the distance to the endpoint so we can qualify for Program 1? The results of any air dispersion…
- Last published:
-
How often must employees complete refresher training?
How often must employees of facilities that are subject to the risk management program complete refresher training? A facility owner or operator must provide refresher training at least every three years, and more often if necessary, to each employee operating a process in order to ensure that the employee understands…
- Last published:
-
Does a PHA for OSHA satisfy EPA's PHA requirement for Program 3?
The risk management program regulations require that an initial process hazard analysis (PHA) for each Program 3 process be completed no later than June 21, 1999 (or by the time the process first has more than a threshold quantity of a regulated substance, if that occurs after June 21, 1999)…