Public Notice: Public Notice: §401 Clean Water Act (CWA) Water Quality Certification for Clear Creek Ecosystem Restoration Project in Butte County, CA
Summary
The U.S. Army Corps of Engineers (USACE) is requesting §401 CWA Water Quality Certification from the Environmental Protection Agency for a USACE CWA 404 permit authorizing grading and bank protection activities in Clear Creek and adjacent wetlands on Tribal trust lands of the Mechoopda Indian Tribe of Chico Rancheria. The purpose of the project is to stabilize streambanks, increase floodplain saturation and restore riparian plants of tribal cultural significance. The project will result in permanent impacts to 0.195 acres of Clear Creek and 0.074 acres of adjacent wetlands.
Section 401 of the Clean Water Act requires applicants for federal licenses or permits that conduct any activity that may result in discharge into waters of the United States to obtain a certification or waiver from the certifying authority where the discharge originates. As the water quality certifying authority for the Mechoopda Indian Tribe of Chico Rancheria, EPA will analyze the discharge from the proposed activities to determine if the restoration project activities will comply with sections of the Clean Water Act. Then EPA will decide whether to (1) certify as proposed; (2) certify with conditions; (3) deny or (4) waive certification of the proposed activities.
Location
The project site is located along Clear Creek upstream of State Route 149 on Mechoopda Tribal lands located northwest of Oroville, on Sections 05 and 06 of Township 20 North, Range 3 East of the Mount Diablo Meridian.
For Further Information Contact
Joseph Morgan, Wetlands and Oceans Section (WTR-2-2)
U.S. Environmental Protection Agency
75 Hawthorne St.
San Francisco, CA 94105
(415) 972-3309
morgan.joseph@epa.gov.
Supplemental Information
The design plan includes targeted hydraulic measures designed for floodplain connection and channel widening. The hydraulic measures will increase flood plain saturation and bank stabilization in key areas. A 5:1 to 6:1 bank slope is proposed for all grading within the channel and adjacent banks. Approximately 3,563 cubic yards of soil will be excavated over 2.21 acres of the creek bed, banks, and adjacent areas.
Supplemental toe rock protection will be placed at all grading sites to reduce erosion potential at the slope toe. Approximately 1,126 cubic yards of cobble 1.5-8 inches in diameter will be placed at the bottom one-third of the slope at the four graded areas. The cobble armoring will cover approximately 0.349 acres. The toe protection is intended to function as a sacrificial measure that slows erosion during flows, including those that may exceed the analyzed 5-year event, rather than permanently fixing the bank in a static position. This temporary protection is intended to provide time for vegetation to become established on the graded slope and bank, after which vegetative roughness and root reinforcement would provide additional long-term erosion resistance.
Riparian planting will occur in a narrow corridor ranging from 20 to 50 feet in width from the channel. Oak woodland plantings along with native shrubs, grasses, and forbs will flank the riparian channel plantings in targeted areas where floodplain connectivity is proposed. The planting palette was recommended and approved by the Mechoopda Tribe for survival capability and cultural value. Planted vegetation will be irrigated during an initial establishment period of five years using on-site well and creek water.
The available construction season is based primarily on water levels in the creek. The in-water construction season is defined as July 1 through October 1 of each year. By limiting construction to occur outside of the rainy season when the creek is expected to be dry, impacts to the water body and to wildlife (including listed species) will be avoided or greatly reduced. Revegetation efforts can proceed year-round unless site conditions preclude work activities. Construction is scheduled to occur in 2027, pending the receipt of funding, and completed within one year.