Skip to main content
U.S. flag

An official website of the United States government

Here’s how you know

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock (LockA locked padlock) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

    • Environmental Topics
    • Air
    • Bed Bugs
    • Chemicals, Toxics, and Pesticide
    • Emergency Response
    • Environmental Information by Location
    • Health
    • Land, Waste, and Cleanup
    • Lead
    • Mold
    • Radon
    • Research
    • Science Topics
    • Water Topics
    • A-Z Topic Index
    • Laws & Regulations
    • By Business Sector
    • By Topic
    • Compliance
    • Enforcement
    • Guidance
    • Laws and Executive Orders
    • Regulations
    • Report a Violation
    • Environmental Violations
    • Fraud, Waste or Abuse
    • About EPA
    • Our Mission and What We Do
    • Headquarters Offices
    • Regional Offices
    • Labs and Research Centers
    • Planning, Budget, and Results
    • Organization Chart
    • EPA History

Breadcrumb

  1. Home
  2. EPA in California
  3. Moss Landing Vistra Battery Fire

Moss Landing Vistra Battery Fire Response: Response Timeline

Moss Landing Vistra Battery Fire Response | Response Timeline | FAQs| Photos | Register for Email Updates

En español

Response Timeline

April 10, 2026

  • Battery removal work continued at a steady pace. Vistra has de-energized more than 27,800 batteries for recycling thus far. No fires started since battery removal work began in July 2025.
  • To reduce dust, Vistra applied a tackifier to the ash footprint.
    • Tackifier is a sticky coating that can be added to surfaces to prevent dust build-up.
    • Tackifier wasn’t applied prior because site conditions were too unsafe. As demolition and stabilization finished, workers were able to safely apply the tackifier.
  • A new industrial elevator was built for crews to access batteries on the second floor of the building.
  • Crews are expected to finish removing intact batteries from the Moss Landing 300 building by May or June 2026.

Phase 2 of battery removal (estimated mid-2026)

  • The second phase of demolition (Phase 2) will address the heavily-burned parts of the building.
    • Once accessible and intact batteries are removed, Phase 2 work will start.
    • Severely-burned and damaged batteries (including battery ash and debris) will be removed during Phase 2.
    • As many batteries as possible will be recycled.
    • The building will be torn down to its foundation.
  • Battery removal work is estimated to continue into at least Fall or Winter 2026.

Safely disposing fire-suppression water

  • Fire suppression water used in the January 2025 fire was collected and stored in a tank on-site. It was sampled and found to be non-hazardous. Then, it was disposed of at the Clean Harbors Seaport facility (San Jose, California).

February 13, 2026

To Date

  • 22,984 batteries de-energized (about 12,788 remaining)
  • Zero flareups during battery removal work.
  • Ten truckloads of batteries (about 19 tons), on average, sent weekly for recycling.
  • Ten more truckloads of waste are sent weekly for disposal and recycling facilities.

Work Progress

  • Phase 1 of building stabilization and partial demolition work at the Moss Landing 300 building done before the holidays.
    • Key areas of the damaged building were stabilized and demolished so workers could safely access and remove batteries.
  • Phase 2 will start after the remaining accessible, intact batteries are removed. Phase 2 (estimated to start in mid-2026) addresses:
    • severely burned sections of the Moss Landing 300 building, including demolition to its foundation, and
    • treatment and disposal of burned and damaged batteries.

Close Agency Oversight

  • We continue daily oversight on-site of Vistra’s work.
  • We also activated the U.S. Coast Guard’s Pacific Strike Team to assist with federal oversight.
    • United States Coast Guard Federal On-Scene Coordinator Representatives have a similar role and training to EPA On-Scene Coordinators (who have been overseeing the cleanup so far).
    • Coast Guard service members help:
      • ensure compliance with federal regulations and response plans and
      • coordinate with various agencies and staff working on the project.

Safety First

  • We continue to ensure Vistra uses best management practices for controlling dust during battery removal.
    • We oversee their air monitoring and air sampling to detect dust and track if it’s moving off-site.
    • Workers follow safety precautions, like removing or cleaning equipment, before leaving the work zone.

Rainy Season Safety Measures

  • We are adding to our safety oversight to accommodate the rainy season.
    • Containing water that enters or is used at the site is central to our approach.
      • Water used in battery removal or building demolition, or water that falls as rain on or near the Moss Landing 300 building, is captured.
      • The capture system is a closed-loop stormwater management system.
      • Captured water is tested for elevated levels of contaminants.
      • Based on the results of this testing, the water is then properly managed (either disposed of off-site at appropriate facilities, reused [if able] on-site, and/or managed in compliance with stormwater discharge procedures).
    • Batteries can re-ignite in wet conditions. In response, we ensure Vistra processes all batteries under tents so they are protected from the rain.
    • Vistra continuously monitors weather conditions so operations can be temporarily stopped, if needed, for safety.

December 19, 2025

During the government shutdown (October 1, 2025 through November 12, 2025), EPA On-Scene Coordinators continued overseeing battery removal as normal.

  • Battery removal work continued at a steady pace, with 8,448 batteries de-energized and transported off-site thus far. To date, there were no flareups during battery removal work.
  • Five truckloads, on average, a week of de-energized batteries left the site for recycling.
    • Each truckload carried about 192 modules on 24 pallets (approximately 37,632 pounds).
    • An additional 10 trucks, on average, carrying other waste and debris, left the site each week for various disposal and recycling facilities.
  • Vistra identified a new battery recycling facility, Cirba Solutions in Lancaster, Ohio, to dispose batteries.
    • We approved the Cirba facility as acceptable for receiving wastes under our Off-Site Rule . We had previously also approved the American Battery Technology Company facility in Nevada.
    • Vistra planned to send batteries to both facilities.
  • Building stabilization and demolition work on the fire-impacted building (Moss Landing 300) continued. This work allowed Vistra to get safe access to the remaining batteries.
  • We continued to oversee Vistra’s work at the site and also activated the U.S. Coast Guard’s Pacific Strike Team to assist with federal oversight.
    • United States Coast Guard Federal On-Scene Coordinator representatives have a similar role and training to EPA On-Scene Coordinators (who have been overseeing the cleanup so far).
    • These Coast Guard service members were responsible for:
      • coordinating the federal response to pollution incidents and emergencies,
      • monitoring compliance with regulations,
      • managing response plans, and
      • coordinating with various agencies and personnel.
  • While battery removal work was occuring, Vistra used best management practices for controlling dust.
    • We continued our oversight of Vistra’s air monitoring and air sampling work.
    • Workers also followed safety precautions like removing or cleaning equipment before leaving the work zone.
  • With the onset of the rainy season, we recognized the importance of ensuring Vistra contained impacted water that entered or was used at the site.
    • Water used in battery removal or building demolition, or water that fell as rain on or near the Moss Landing 300 building, was captured.
    • The capture system was a closed-loop stormwater management system.
    • Captured water was tested for elevated levels of contaminants.
    • Based on this testing, the water was then properly managed (either disposed of off-site at appropriate facilities, reused [if able] on-site, and/or managed in compliance with stormwater discharge procedures).
  • We recognize batteries can re-ignite in wet conditions. All batteries being processed—whether they are being staged, de-energized, or packaged for transport—are protected from rain under tents.
    • Additionally, Vistra continuously monitored weather conditions so operations could be temporarily stopped if needed for safety.
  • Cleanup work paused from December 19th – December 28th. However:
    • fire crews continued monitoring the site for any potential flareups, and
    • all air monitoring and air sampling around the site and in the community continued during this time.

September 29, 2025

On September 29, 2025, workers began removing the first set of batteries from the Moss Landing 300 building. This marks a major milestone in the battery removal process.

A significant focus was to ensure battery removal was safe and efficient (pdf). For weeks, teams practiced safe battery removal handling and processing procedures. This was done while limited demolition and building stabilization happened.

  • Battery removal for most of 2025 focused on “intact” batteries, batteries with no damage or minor damage from the fire.
  • Workers de-energized these batteries and transferred any remaining energy back into the local electrical grid.

See our Community Involvement Plan for more information on the battery processing process. As with all work, we ensured strict health and safety requirements, and best practices were always followed.

The Moss Landing Administrative Record was made available for public comment through October 15, 2025. EPA received no comments during the comment period.

The Administrative Record contains documents that justify EPA directing response activities at the site. A paper copy of the Administrative Record can be found at:
Castroville Branch Library
11160 Speegle St.
Castroville, CA 95012
Please call for current hours of operation: (831) 769-8724.


September 16, 2025

We are committed to transparency. To share information on this project, we have developed the  Moss Landing Battery Fire Community Involvement Plan (pdf) (4.25 MB, September 16, 2025) .

  • To create the plan, we interviewed 17 community members, local officials, organizations, and other stakeholders.
  • The interviews and other research helped us identify information gaps and things to keep in mind as we share information and engage the community throughout this project.
  • We developed and will implement the plan with support from Vistra.

Many thanks to the Monterey community members who volunteered to be interviewed. Your thoughtful, heart-felt contributions were the basis for this plan and we appreciate your openness to share with us.


August 2025

  • EPA continues to provide on-site technical assistance and oversight of battery removal process.
  • Equipment arrives at the site (such as cranes).
  • Preliminary building stabilization work in key areas of the “Moss Landing 300” building (which was burned in the fire) in order for crews to more safely access batteries.
  • Perform building stabilization work.
  • Start a “surgical” removal of certain portions of the burned building so some batteries can be safely accessed.
  • Remove the batteries from the damaged building for on-site processing.
  • Start removing (de-energizing) energy from those batteries.

July 17, 2025

On July 17, 2025, EPA entered into an agreement with Vistra to remove damaged batteries from its property.

  • The agreement covers the battery removal preparation and planning work that Vistra has been doing voluntarily and future work.
  • Building stabilization and demolition planning is underway to safely access the batteries.
  • All battery removal work will be done under our close oversight. We are coordinating with Monterey County throughout.
EPA and Vistra personnel surveying damage to the “ML300” building.
EPA and Vistra staff inspecting damage to Vistra’s building post-fire. Click to enlarge.

Before reaching the agreement with Vistra in July 2025 on the battery removal process, the following activities were completed on site:

  • Disconnected (delinked) batteries from the building’s infrastructure for safety.
  • Removed fire debris with asbestos from part of the damaged building.
    • Debris was safely transported and disposed of at the Forward Landfill. The landfill is in Manteca, Calif., about 135 miles northeast of Monterey.
  • Removed about 586,300 gallons (about as much as an Olympic-sized swimming pool) water that was stored in tanks on the property. The water was sampled, determined to be non-hazardous and sent for disposal.

March-July, 2025

  • Negotiated agreement outlining Vistra’s obligations and clarifying the EPA’s expectations for the battery removal process.
  • Developed and performed thorough technical reviews on over 30 detailed plans and procedures in preparation for safe battery removal, partial building demolition, and building stabilization.
The building that caught on fire is next to the smoke stacks formerly part of energy generation. The stacks are iconic locally.
The building that caught on fire is next to the smoke stacks formerly part of energy generation. The stacks are iconic locally. Click to enlarge.

March 13, 2025

  • Battery delinking complete.

February 22, 2025

  • Battery delinking begins.

February 18, 2025

  • Flareup inside building occurs, causing smoke in the building. Visible flareup subsided.
  • State of California Environmental Protection Agency requests EPA lead the oversight of Vistra’s battery removal work.

January 22, 2025

  • EPA issues Notice of Federal Response Action to Vistra.
    • The notice documents why an urgent response to the fire is needed.
    • It also outlines the work that needs to be done to address hazardous substances on the site.
  • Vistra confirms it will voluntarily do the response.
  • EPA then begins providing technical assistance to Vistra for the battery removal process and reviews Vistra's plans for battery removal.
View of the fire from staging area.
Smoke Plume. Click to enlarge.

January 20, 2025

  • After smoke subsides, EPA consults with Monterey County and transfers air monitoring stations to Vistra.

January 18, 2025

  • Fire goes out.

January 17, 2025

  • EPA begins perimeter air monitoring early the morning of Jan. 17.
  • EPA sets up nine air monitoring locations at and around the site.
  • The monitors look for mineral acid gases (like hydrogen fluoride) and particulates.

January 16, 2025

  • Battery fire starts at Vistra's energy storage facility. The facility has about 100,000 battery modules.
  • Local agencies respond and request EPA assistance with perimeter air monitoring.

What caused the fire?

Vistra, and the battery manufacturer, are still investigating the cause of the fire.

EPA in California

  • Topics and Resources
    • California Bioresources Alliance Symposia
      • 2024
      • 2023
      • 2022
      • 2021
      • 2020
      • 2019
      • 2018
      • 2017
      • 2016
    • Central Metal Site Investigation
      • Frequently Asked Questions (FAQs)
      • Investigación del sitio de Central Metal
      • Preguntas Frecuentes
    • Former Exide Battery Recycling Facility
      • En español
      • Archived Updates
    • Kettleman Hills
      • Permit and Supporting Documents
  • Moss Landing Vistra Battery Fire
    • Response Timeline
    • Frequently Asked Questions
    • Photographs
    • Register for Email Updates
  • Incendio de la batería Vistra en Moss Landing
    • Cronograma de respuesta
    • Preguntas frecuentes
    • Fotografías
    • Únase a la lista de distribución por correo electrónico
Contact Us About EPA in California
Contact Us About EPA in California to ask a question, provide feedback, or report a problem.
Last updated on April 14, 2026
  • Assistance
  • Spanish
  • Arabic
  • Chinese (simplified)
  • Chinese (traditional)
  • French
  • Haitian Creole
  • Korean
  • Portuguese
  • Russian
  • Tagalog
  • Vietnamese
United States Environmental Protection Agency

Discover.

  • Accessibility Statement
  • Budget & Performance
  • Contracting
  • EPA www Web Snapshot
  • Grants
  • No FEAR Act Data
  • Plain Writing
  • Privacy and Security Notice

Connect.

  • Data
  • Inspector General
  • Jobs
  • Newsroom
  • Regulations.gov
  • Subscribe
  • USA.gov
  • White House

Ask.

  • Contact EPA
  • EPA Disclaimers
  • Hotlines
  • FOIA Requests
  • Frequent Questions
  • Site Feedback

Follow.